Custom Built Industrial Refrigeration Systems by Mullally Bros.

Ace Endico Fine Foods Purveyor and Distributor

Brewster, NY

Freezer and Dock Addition – 2018

This long-term customer added 30,000 sq ft of -10°F Freezer space, 10,000 sq ft of +36°F Dock, and a 4,000 sq ft -20°F Ice Cream Freezer.  Design/Build for total refrigeration scope, including:

  • 9 New Evaporators in the Freezer and Dock
  • 2 New R404a Split Systems for the Ice Cream Freezer
  • 1 New Compressor and Condenser
  • Underfloor Heat in the Freezers and Heated Sidewalks and Truck Ramps
  • Design will Accommodate a Convertible Addition of 23,000 sq ft of Future Freezer or Cooler

Pepsi Bottling Group

Latham, NY

Replace Two Condensers, High Stage Discharge and Condenser Pipe – 2018

  • Removed 2 Condensers and Structural Steel down to the Piers and Installed 1 New Galvanized Platform and Stairs
  • Installed New 9500 MBH All Stainless-Steel Frick IDCS Condenser
  • Also Installed an Evapco Fluid Cooler Dedicated to Compressor Oil and Head Cooling

DeIorio’s Frozen Dough

Utica, NY

R-22 to Ammonia Spiral Freezer Conversion – 2017

Our long-term customer needed to convert their -20°F Spiral Freezers from R-22 to Ammonia.  We delivered a 100% turnkey solution to them:

  • Designed, Constructed and Installed Brand-new 175 Ton Ammonia System
  • Pump Package Designed and Built In-House with a Frick Vessel
  • Compressor Room Construction, Electrical and Insulation Contractors all worked under Mullally Bros, Inc.

What Our Clients Say

“I wanted to express our great appreciation for the way this heat exchanger project went down.  You heard us loud and clear that our downtime would be extremely expensive if it started stacking up milk to the point that it couldn’t make its way to processing.  You made sure this didn’t happen, and indeed, exceeded expectations.  Tony did everything possible to prepare for a speedy and accurate installation.  I was most impressed with the way your entire crew worked together and really bore down in it until completed.  Tom was also instrumental in compressing the operation.  I hope I passed this on to all the guys as they were getting ready to head out Wed.  morning.  I think I saw it in all faces that they had a satisfaction in the job outcome and the kudos they heard from us.”

Allen Yanney, Facilities and Maintenance Manager
St. Albans Cooperative Creamery, Inc.